405 Huntmar (D07-12-22-0186)

405 Huntmar (D07-12-22-0186) #

Summary #

Application StatusPost Approval
Review StatusAgreement Signed
DescriptionTwo new light-industrial buildings of approximately 21,398 sq. m. and 23,095 sq. m. respective. Each building will be divided into four individual units. Units are intended to be leased and the site is not proposed to be subdivided.
WardWard 4 - Cathy Curry
Date Initiated2022-12-27
Last Updated2024-10-11

Renders #

  • Rendering of building from page 9 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Rendering of building from page 16 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Rendering of building from page 25 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Rendering of building from page 24 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Rendering of building from page 24 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Rendering of building from page 9 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Rendering of building from page 16 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Rendering of building from page 25 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Rendering of building from page 24 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Rendering of building from page 24 of the file '2022-12-28 - Design Brief - D07-12-22-0186'

Site and Floor Plans #

  • Construction site plan for project from page 3 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 4 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 4 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 4 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 5 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 5 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 6 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 6 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 8 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 17 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 20 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 3 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 4 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 4 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 4 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 5 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 5 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 6 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 6 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 8 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 17 of the file '2022-12-28 - Design Brief - D07-12-22-0186'
  • Construction site plan for project from page 20 of the file '2022-12-28 - Design Brief - D07-12-22-0186'

Documents #

TypeDocument
Application Summary2023-01-18 - Application Summary - D07-12-22-0186
Architectural PlansPOST-DEVELOPMENTSTORMWATER MANAGEMENT PLAN
Architectural Plans2024-02-07 - Plan and Profile - D07-12-22-0186
Architectural Plans2023-12-13 - Plan and Profile - D07-12-22-0186
Architectural Plans2023-12-13 - General Plan of Services - D07-12-22-0186 (2)
Architectural Plans2023-12-13 - GENERAL PLAN OF SERVICES - D07-12-22-0186
Architectural Plans2023-10-20 - Approved Site Plans - D07-12-22-0186
Architectural Plans2023-10-20 - Approved Plan and Profile-Off-Site Watermain Extension Station - D07-12-22-0186
Architectural Plans2023-10-20 - Approved General Plans of Services 1 & 2 - D07-12-22-0186
Architectural Plans2023-10-20 - Approved Building Elevations - D07-12-22-0186
Architectural Plans2023-09-21 - Site Plans - D07-12-22-0186
Architectural Plans2023-09-21 - Plan and Profile - D07-12-22-0186
Architectural Plans2023-09-21 - General Plans of Services - D07-12-22-0186
Architectural Plans2023-08-08 - Site Plan - D07-12-22-0186
Architectural Plans2023-08-08 - Plan and Profile - D07-12-22-0186
Architectural Plans2023-08-08 - GENERAL PLAN OF SERVICES - D07-12-22-0186 (2)
Architectural Plans2023-08-08 - GENERAL PLAN OF SERVICES - D07-12-22-0186
Architectural Plans2023-06-02 - Site Plans - D07-12-22-0186
Architectural Plans2023-06-02 - Plan and Profile - D07-12-22-0186
Architectural Plans2023-06-02 - General Plan of Services - D07-12-22-0186 (2)
Architectural Plans2023-06-02 - General Plan of Services - D07-12-22-0186
Architectural Plans2023-04-04 - Plan & Profile - D07-12-22-0186
Architectural Plans2023-04-04 - General Plan of Services - D07-12-22-0186 (2)
Architectural Plans2023-04-04 - General Plan of Services - D07-12-22-0186
Architectural Plans2023-04-04 - Context Plan , Site Plan, Site Details - D07-12-22-0186
Architectural Plans2022-12-28 - Site Plan and Details - D07-12-22-0186
Architectural Plans2022-12-28 - Plan and Profile-Off-Site Watermain Extension - D07-12-22-0186
Architectural Plans2022-12-28 - General Plan of Services - D07-12-22-0186
Architectural Plans2022-12-28 - Building Elevations - D07-12-22-0186
Design Brief2022-12-28 - Design Brief - D07-12-22-0186
Environmental2022-12-28 - Phase I Environmental Site Assessment - D07-12-22-0186
Environmental2022-12-28 - Environmental Noise Control Study - D07-12-22-0186
Erosion And Sediment Control Plan2023-10-20 - Approved Erosion and Sediment Control Plan - D07-12-22-0186
Erosion And Sediment Control Plan2023-09-21 - Erosion & Sediment Control Plan - D07-12-22-0186
Erosion And Sediment Control Plan2023-08-08 - EROSION AND SEDIMENT CONTROL PLAN - D07-12-22-0186
Erosion And Sediment Control Plan2023-06-02 - Erosion and Sediment Control Plan - D07-12-22-0186
Erosion And Sediment Control Plan2023-04-04 - Erosion & Sediment Control Plan - D07-12-22-0186
Erosion And Sediment Control Plan2022-12-28 - Erosion and Sediment Control Plan - D07-12-22-0186
Geotechnical Report2023-10-20 - Approved Grading Plans 1 & 2 - D07-12-22-0186
Geotechnical Report2023-09-21 - Grading Plans - D07-12-22-0186
Geotechnical Report2023-08-08 - Grading Plan - D07-12-22-0186 (2)
Geotechnical Report2023-08-08 - Grading Plan - D07-12-22-0186
Geotechnical Report2023-06-02 - Grading Plan - D07-12-22-0186 (2)
Geotechnical Report2023-06-02 - Grading Plan - D07-12-22-0186
Geotechnical Report2023-06-02 - Geotechnical Recommendations -Grading and Landscaping Plan Review - D07-12-22-0186
Geotechnical Report2023-06-02 - Geotechnical Investigation - D07-12-22-0186
Geotechnical Report2023-04-04 - Grading Plan - D07-12-22-0186 (2)
Geotechnical Report2023-04-04 - Grading Plan - D07-12-22-0186
Geotechnical Report2023-04-04 - Geotechnical Investigation - D07-12-22-0186
Geotechnical Report2022-12-28 - Grading Plans - D07-12-22-0186
Geotechnical Report2022-12-28 - Geotechnical Investigation - D07-12-22-0186
Landscape Plan2023-10-20 - Approved Landscape Plan - D07-12-22-0186
Landscape Plan2023-10-13 - Landscape Plan - D07-12-22-0186
Landscape Plan2023-09-21 - Landscape Plans and Details - D07-12-22-0186
Landscape Plan2023-08-08 - Landscape Plan - D07-12-22-0186
Landscape Plan2023-06-02 - Landscape Plans - D07-12-22-0186
Landscape Plan2023-04-04 - Landscape Plan - D07-12-22-0186
Landscape Plan2022-12-28 - Landscape Plan - D07-12-22-0186
Notification2024-02-07 - Commence Work Notification - Registration of Agreement - D07-12-22-0186
Notification2023-12-13 - Commence Work Notification Registration of Agreement - D07-12-22-0186
Planning2022-12-28 - Planning Rationale - D07-12-22-0186
Shadow Study2023-06-02 - FIRE FLOW - D07-12-22-0186
Shadow Study2023-04-04 - Required Fire Flow Proposal Letter - D07-12-22-0186
Shadow Study2023-04-04 - FIRE ROUTE PLAN - D07-12-22-0186
Shadow Study2023-04-04 - FIRE FLOW with SEAL Letter - D07-12-22-0186
Site Servicing2023-09-21 - Site Servicing and Stormwater Management Report - D07-12-22-0186
Site Servicing2023-08-08 - Site Servicing and Stormwater Management Report - D07-12-22-0186
Site Servicing2023-06-02 - Site Servicing & Stormwater Management Report - D07-12-22-0186
Site Servicing2023-04-04 - Site Servicing & Stormwater Management Report - D07-12-22-0186
Site Servicing2023-01-20 - Site Servicing & SWM Report - D07-12-22-0186
Stormwater Management2023-10-20 - Approved Post-Development Stormwater Management Plan - D07-12-22-0186
Stormwater Management2023-09-21 - Post-Development SWM Plan - D07-12-22-0186
Stormwater Management2023-08-08 - POST-DEVELOPMENT Stormwater Management Plan - D07-12-22-0186
Stormwater Management2023-06-02 - Post-Development Stormwater Management Plan - D07-12-22-0186
Stormwater Management2023-04-04 - POST-DEVELOPMENT STORMWATER MANAGEMENT PLAN - D07-12-22-0186
Stormwater Management2022-12-28 - Post-Development Stormwater Management Plan - D07-12-22-0186
Surveying2022-12-28 - Plan of Survey - D07-12-22-0186
Transportation Analysis2023-04-04 - Transportation Impact Assessment - D07-12-22-0186
Transportation Analysis2022-12-28 - Transportation Impact Assesment - D07-12-22-0186
Tree Information and Conservation2023-10-13 - Scoped Environmental Impact Assessment and Tree Conservation Report - D07-12-22-0186
Tree Information and Conservation2023-09-21 - Addendum to the Scoped Environmental Impact Statement and TCR - D07-12-22-0186
Tree Information and Conservation2022-12-28 - Preliminary Scoped Environmental Impact Statement and TCR - D07-12-22-0186
2023-10-20 - Signed Delegated Authority Report - D07-12-22-0186
2023-10-20 - Approved Notes, Legend and Details 1 & 2 - D07-12-22-0186
2023-09-21 - Notes Legend and Details - D07-12-22-0186
2023-08-08 - NOTES LEGEND AND DETAILS - D07-12-22-0186 (2)
2023-08-08 - NOTES LEGEND AND DETAILS - D07-12-22-0186
2023-06-02 - Notes, Legend and Details - D07-12-22-0186 (2)
2023-06-02 - Notes, Legend and Details - D07-12-22-0186
2023-04-04 - Roof Drainage Declaration - D07-12-22-0186
2023-04-04 - Notes Legend & Details - D07-12-22-0186 (2)
2023-04-04 - Notes Legend & Details - D07-12-22-0186
2022-12-28 - Roadway Modification Application - D07-12-22-0186
2022-12-28 - Engineering Notes, Legend and Details - D07-12-22-0186