2190 Halifax/2145 Walkley (D07-12-19-0075)

2190 Halifax/2145 Walkley (D07-12-19-0075) #

Summary #

Application StatusActive
Review StatusComment Period in Progress
DescriptionDevelopment of a 15 storey + penthouse high rise residential building.
WardWard 18 - Marty Carr
Date Initiated2019-05-08
Last Updated2025-01-31

Renders #

  • Rendering of building from page 1 of the file '2019-08-15 - Arch Rendering - D07-12-19-0075'
  • Rendering of building from page 1 of the file '2019-08-15 - Arch Rendering - D07-12-19-0075'

Site and Floor Plans #

  • Construction site plan for project from page 1 of the file '2019-08-15 - P1 Floor Plan - D07-12-19-0075'
  • Construction site plan for project from page 1 of the file '2019-08-15 - P1 Floor Plan - D07-12-19-0075'

Files #

TypeNameLinks
Application Summary2019-09-09 - Application Summary - D07-12-19-0075Download PDF
Application Summary2025-01-31 - Updated Application Summary - D07-12-19-0075Download PDF
Architectural Plans2019-08-15 - Site Sections Plan - D07-12-19-0075Download PDF
Architectural Plans2019-08-15 - Site Plan - D07-12-19-0075Download PDF
Architectural Plans2019-08-15 - Key Plan & Zoning Table - D07-12-19-0075Download PDF
Architectural Plans2019-08-15 - Elevations - D07-12-19-0075Download PDF
Architectural Plans2024-12-20 - Architectural Plans - D07-12-19-0075Download PDF
Architectural Plans2025-03-26 - MEMO - Grading Plan Review - D07-12-19-0075Download PDF
Architectural Plans2025-03-26 - Key and Site Plan - D07-12-19-0075Download PDF
Architectural Plans2025-08-21 - Site Plan - D07-12-19-0075Download PDF
Architectural Plans2025-08-21 - P2 and P3 Parking Garage Plans - D07-12-19-0075Download PDF
Architectural Plans2025-08-21 - Key Plan and Zoning Table - D07-12-19-0075Download PDF
Civil Engineering Report2019-08-15 - Civil Package - D07-12-19-0075Download PDF
Civil Engineering Report2024-12-20 - Civil Drawings - D07-12-19-0075Download PDF
Civil Engineering Report2025-03-26 - Civil Drawings - D07-12-19-0075Download PDF
Environmental2019-08-15 - Phase II ESA - D07-12-19-0075Download PDF
Environmental2019-08-15 - Phase I ESA - D07-12-19-0075Download PDF
Environmental2024-12-20 - Phase II ESA - D07-12-19-0075Download PDF
Environmental2024-12-20 - Phase I ESA - D07-12-19-0075Download PDF
Floor Plan2019-08-15 - P2 Floor Plan - D07-12-19-0075Download PDF
Floor Plan2019-08-15 - P1 Floor Plan - D07-12-19-0075Download PDF
Geotechnical Report2019-08-15 - Geotech Report - D07-12-19-0075Download PDF
Geotechnical Report2025-03-26 - Geotechnical Investigation - D07-12-19-0075Download PDF
Geotechnical Report2025-08-21 - Geotechnical Investigation - D07-12-19-0075Download PDF
Landscape Plan2019-08-15 - Landscape Plan - D07-12-19-0075Download PDF
Landscape Plan2024-12-20 - Landscape Plan - D07-12-19-0075Download PDF
Landscape Plan2025-03-26 - LANDSCAPE PLAN - D07-12-19-0075Download PDF
Landscape Plan2025-08-21 - Landscape Plan - D07-12-19-0075Download PDF
Planning2019-08-15 - Planning Rationale - D07-12-19-0075Download PDF
Rendering2019-08-15 - Renderings - D07-12-19-0075Download PDF
Rendering2019-08-15 - Arch Rendering - D07-12-19-0075Download PDF
Shadow Study2019-08-15 - Sun-Shadow Analysis - D07-12-19-0075Download PDF
Site Servicing2019-08-15 - Servicing Report - D07-12-19-0075Download PDF
Site Servicing2024-12-20 - Site Servicing Report - D07-12-19-0075Download PDF
Site Servicing2025-03-26 - Site Servicing Report - D07-12-19-0075Download PDF
Site Servicing2025-08-21 - Site Servicing Report - D07-12-19-0075Download PDF
Site Servicing2025-08-21 - Site Servicing Plan - D07-12-19-0075Download PDF
Surveying2019-08-15 - Survey Plan - D07-12-19-0075Download PDF
Transportation Analysis2019-08-15 - TIA - D07-12-19-0075Download PDF
Transportation Analysis2024-12-30 - Transportation Impact Assessment Addendum Letter - D07-12-19-0075Download PDF
Transportation Analysis2025-03-26 - Traffic Impact Assessment - D07-12-19-0075Download PDF
Transportation Analysis2025-08-21 - Transportation Impact Assessment - D07-12-19-0075Download PDF