2555 Marchurst/2625 Marchurst (D02-02-25-0050)

2555 Marchurst/2625 Marchurst (D02-02-25-0050) #

Summary #

Application StatusActive
Review StatusComment Period in Progress
DescriptionThe City of Ottawa has received a Zoning By-law Amendment application to facilitate the development of a Battery Energy Storage System (BESS) facility at 2555 and 2625 Marchurst Road proposing 256 BESS containers, a substation, a stormwater pond, a transmission line connection, a noise wall, with an access from Marchurst Road.
WardWard 5 - Clarke Kelly
Date Initiated2025-07-14
Last Updated2025-10-22

Documents #

TypeDocument
Application Summary2025-10-21 - Application Summary - D02-02-25-0050
Archaelogical Assessment2025-07-14 - Stage 1 Archaeological Assessment - D02-02-25-0050
Architectural Plans2025-10-09 - Site Plan Sheet 2 - D02-02-25-0050
Architectural Plans2025-10-09 - Site Plan Sheet 1 - D02-02-25-0050
Architectural Plans2025-10-09 - Emergency Response Plan - D02-02-25-0050
Architectural Plans2025-10-09 - BESS Decommissioning Plan - D02-02-25-0050
Architectural Plans2025-10-09 - BESS Commissioning Plan - D02-02-25-0050
Architectural Plans2025-07-14 - Wet Pond Plan & Sections - D02-02-25-0050
Architectural Plans2025-07-14 - Site Plan Sheet 2 - D02-02-25-0050
Architectural Plans2025-07-14 - Site Plan Sheet 1 - D02-02-25-0050
Architectural Plans2025-07-14 - Preliminary Construction Management Plan - D02-02-25-0050
Architectural Plans2025-07-14 - Emergency Response Plan - D02-02-25-0050
Architectural Plans2025-10-24 - BESS Decommissioning Plan - D02-02-25-0050
Architectural Plans2025-10-24 - BESS Commissioning Plan - D02-02-25-0050
Civil Engineering Report2025-07-14 - Civil - Cover Page & Drawing Index - D02-02-25-0050
Environmental2025-10-09 - Environmental Impact Study - D02-02-25-0050
Environmental2025-07-14 - Environmental Impact Study - D02-02-25-0050
Erosion And Sediment Control Plan2025-07-14 - Erosion and Sediment Control Details - D02-02-25-0050
Erosion And Sediment Control Plan2025-07-14 - Erosion and Sediment Control - D02-02-25-0050
Geotechnical Report2025-10-09 - Hydrogeological and Terrain Analysis Study - D02-02-25-0050
Geotechnical Report2025-07-14 - Hydrogeological and Terrain Analysis Study - D02-02-25-0050
Geotechnical Report2025-07-14 - Grading and Drainage Plan (Roads and Finished Grade Plan) - D02-02-25-0050
Geotechnical Report2025-07-17 - Geotechnical Investigation - D02-02-25-0050
Landscape Plan2025-10-09 - Landscape Plan - D02-02-25-0050
Landscape Plan2025-07-14 - Landscape Plans - D02-02-25-0050
Noise Study2025-10-30 - Initial Noise Memo - D02-02-25-0050
Planning2025-10-09 - Zoning Confirmation Report - D02-02-25-0050
Planning2025-10-09 - Planning Rationale - D02-02-25-0050
Planning2025-07-14 - Zoning Confirmation Report - D02-02-25-0050
Planning2025-07-14 - Planning Rationale - D02-02-25-0050
Site Servicing2025-10-09 - Site Servicing Study - D02-02-25-0050
Site Servicing2025-07-14 - Site Servicing Study - D02-02-25-0050
Site Servicing2025-07-14 - Site Servicing and Fire Protection Plan - D02-02-25-0050
Stormwater Management2025-07-14 - SWM and Water Budget Report (Civil Design Criteria) - D02-02-25-0050
Stormwater Management2025-07-14 - Stormwater and Water Network Details - D02-02-25-0050
Surveying2025-10-09 - Plan of Survey - D02-02-25-0050
Surveying2025-07-14 - Plan of Survey - D02-02-25-0050
Tree Information and Conservation2025-10-09 - Tree Conservation Report - D02-02-25-0050
Tree Information and Conservation2025-07-14 - Tree Conservation Report - D02-02-25-0050
2025-10-09 - Plume Analysis - D02-02-25-0050
2025-10-09 - Fluvial Geomorphology Assessment - D02-02-25-0050
2025-07-14 - Site Grading Profiles - D02-02-25-0050
2025-07-14 - Security Fencing Chain Link Fence Standard Details - D02-02-25-0050
2025-07-14 - Road and Drainage Details - D02-02-25-0050
2025-07-14 - Hazard Mitigation Analysis - D02-02-25-0050
2025-07-14 - General Notes, Legend and Abberviations - D02-02-25-0050
2025-07-14 - Fluvial Geomorphology Assessment - D02-02-25-0050